| Client Brief | |
Our client wanted a reasonably priced training pool for British National swimmers and triathlon swimmers. | |
| Click to enlarge | |
| Pool Design and Equipment | |
We designed a system that would be effective, but could be upgraded in the future i.e. the pool is concrete built with the option to tile at a later date. The pool building is of steel construction using the insulated Kingspan system on the roof and walls to minimize heat loss. | |
| Click to enlarge | |
| The pool filtration and heating system is run as two systems, one covering one half of the pool and the second the other half. This gives the client much more flexibility in the running of the pool so they can run one system in times of low use. | |
| Click to enlarge | |
The pool approximately holds 70,000 gallons with a turnover of 5 hours. The filtration is via Certikin commercial pumps and filters keeping the water very clear and clean. The heating is via two 250,000 BTU oil boilers linked to two Bowmans heater exchangers keeping the water temperature at 28 C. | |
| Click to enlarge | |
For the air conditioning we are using 3 Amcor Commercial dehumidifiers which are comfortably keeping the humidity at 65% with the option of upgrading to a Delta system in the future. |
50 metre Training pool |
Bayleisure.co.uk. Powered by Zen Cart